A
LOCATION: Conowingo Dam, Cecil and Hartford County, MD
STATUS: Active
ISSUE IN BRIEF: After years of delays by Constellation – the owner of Conowingo Dam – the state of Maryland will soon be determining the environmental requirements needed as part of its water quality certification for the dam. Constellation needs this certification before it can obtain its federal hydro-electric dam license.
BACKGROUND: Constellation’s current license expired in 2014. Constellation is seeking a new 50-year license from the Federal Energy Regulatory Commission (FERC). Under Section 401 of the Clean Water Act, the State of Maryland must issue a Water Quality Certification, certifying that the project will meet state water quality standards before FERC can grant a new license.
The state of Maryland issued its Water Quality Certification on April 27, 2018, and Constellation (formerly Exelon, but will be referred to by their current name, Constellation) sued the state on May 25 in federal district court, challenging the state’s authority to require any pollution reduction from upstream sources. On July 20, 2018, Lower Susquehanna Riverkeeper and Waterkeepers Chesapeake represented by Earthjustice, filed a motion to intervene in a federal court action regarding the relicensing of the Conowingo Dam, supporting the state’s authority under the Clean Water Act. This motion to intervene was denied.
In addition, our organizations filed an administrative appeal on June 8, 2018, urging the Maryland Department of the Environment to reconsider its water quality certification for the Conowingo Dam arguing that is incomplete because it is missing several key elements. The state of Maryland must certify that the dam’s operations will not adversely impact water quality under the Clean Water Act. MDE has yet to address the issues in our appeal.
On October 29, 2019, MDE and Constellation announced a settlement agreement made behind closed doors that falls far short of protecting Maryland’s waterways and requires the state to waive its 401 authority to protect local water quality from impacts of dams, without any details on how the agreement will protect water quality. Affected communities and groups, Lower Susquehanna Riverkeeper and Waterkeepers Chesapeake were excluded from the discussions. As it is now, virtually all of the substantive portions of the settlement will not be incorporated into the 50-year federal license agreement – which means there is no public input, scrutiny and, more importantly, no ability to enforce these provisions. In addition, the settlement provides grossly insufficient funds to deal with the risks that Conowingo operations pose to the Susquehanna River and Chesapeake Bay — primarily from the next large storm that will scour the millions of tons of sediment, nutrients, and debris currently trapped behind the dam.
The Conowingo Dam is located on the Lower Susquehanna River about 10 miles upstream from where it flows into the Chesapeake Bay at Havre De Grace, Maryland. As a hydropower dam, Conowingo has replaced a free-flowing section of the Susquehanna River with a 14-mile-long, 9,000-acre reservoir. This fundamentally alters the river’s ecology.
Ever since the dam was built in 1928, it has changed seasonal river flow; blocked the migration of shad, herring, eel and other fish; destroyed fragile aquatic habitat; devastated the shellfish communities that naturally filtered the Susquehanna’s water; killed millions of fish caught in hydroelectric turbines; and altered the river’s natural ability to transport nutrients and sediment. Nearly 200 million tons of sediment pollution have accumulated behind the dam. During major floods caused by large storms, powerful floodwaters can scoop out or “scour” the stored sediment behind the dam and send that downstream to the Chesapeake Bay.
In the case of Conowingo there are laws that dictate how the hydroelectric dam gets relicensed, such as the Clean Water Act. The Federal Power Act. Section 401 of the Clean Water Act gives Maryland the absolute right to issue a Water Quality Certification (WQC) which includes conditions the state concludes would protect water quality in the Susquehanna River and Chesapeake Bay for the next 50 years of dam ownership. You may ask, how does Maryland make these conclusions? Five years before a hydroelectric dam’s license expires they must apply for a new license and at that time it is determined what studies must be completed to mitigate the environmental and recreational impacts of the dam.
Unfortunately, the studies which were provided by Constellation to Maryland were inadequate and more research was requested by the state in order to issue a WQC. One study titled the Lower Susquehanna River Watershed Assessment (LSRWA) which models sediment transport throughout the Lower Susquehanna River dams, was heavily relied on by researchers but was in fact terribly flawed. The study did not model any storm event larger than Tropical Storm Lee in 2011 which was a 20-year return flood. Not one scientist of any NGO neither the federal and state government nor any employee of Constellation knows the consequences to the Chesapeake Bay if another large storm like Hurricane Agnes rolls through our watershed. It simply is not modeled in the LSRWA or any other study.
What we do know is this, scour from behind the dam is known to occur at flows of 175,000 cfs or lower. In 2018 the average flow for the entire year was 71,600 cfs and we had 26 days where flow was above 175,000 cfs at the Conowingo Dam. Captains all around the upper bay had to cease their charters due to sediment, debris and trash coming through Conowingo Dam. Believe it when we say that this dam is a ticking time bomb. The commercial seafood industry in Maryland and Virginia combined generates $3.39 billion in sales, $890 million in income, and nearly 34,000 jobs for the local economy per year. This industry will be wiped out not if, but when, we experience another large storm event like Hurricane Agnes.
The Susquehanna River is a public resource and should not be sold off to a private company for exclusive use without ensuring that the impacts to the public have been properly mitigated. Our team’s work on introducing bipartisan legislation will level the playing field, as MDE will not be able to blindly waive their right to a 401 Water Quality Certification in the proposed settlement, if passed. The 401 Water Quality Certification issued in April 2018 has substantive provisions that must be considered in this settlement. It would be hypocritical for MDE to waive its right, in addition to setting bad precedent for the state and the rest of the country. Again, the settlement provides grossly insufficient funding to mitigate the dam’s operations over the next 50 years. This simply cannot happen as the settlement provides roughly $78 million over the 50-year license term while the substantive State Water Quality Certification required over $8 billion over 50 years.
Given Constellation’s profitability, a company this size should be giving back to the environment and its people what has freely been given to them, rights to a public resource for pure profit. And given their profitability, increased funding should not be an issue for Constellation. They remain the most lucrative utility company in the entire country and must pay their fair share for exclusive use of the Lower Susquehanna River. The financially insufficient proposed settlement poses a firm roadblock to any genuine path forward to the cleanup of the Conowingo Dam and any assurance that Maryland can meet our TMDL and climate goals. More info at Conowingodam.org.
THE LATEST:
Our successful court victory a little over a year ago invalidated the federal license for Conowingo Dam. This needed to happen. The Federal Energy Regulatory Commission (FERC) acted unlawfully by allowing a secret closed-door deal between the state of Maryland and Constellation Energy to be included as conditions in the dam’s federal license. We stopped that from happening and have set a national precedent for the Clean Water Act’s intentions to protect water quality.
The next steps are critical to preserve the integrity of our waters, and we have front-row seats to shape how this will play out. We will be meeting with Constellation Energy and Maryland Department of the Environment to discuss relicensing issues throughout a series of mediated discussions. Our goal is to be able to come to an agreement that ensures Constellation will operate their dam in a way that will make certain water quality is protected for the next generation. More to come…
Lower Susquehanna Riverkeeper Ted Evgeniadis presents to The Society of Environmental Journalists at Conowingo Dam April 4, 2024 -photo by: Fred Tutman. Photo file name: IMG_2034-1024x683
IN THE MEDIA:
-
Bay Journal: Debate resumes on Conowingo Dam pollution problems - 6/22/23
-
Baltimore Sun: Federal court invalidates 50-year license for Maryland’s Conowingo Dam, a win for environmental groups - 12/20/22
-
The Washington Post: Judges kill deal to help Md. power company avoid bay cleanup - 12/20/22
-
Cecil Whig: Federal court overturns Conowingo Dam license - 12/20/22
-
Maryland Matters: Opinion: Does Hogan Care More About Wealthy Corporations Than the Bay? - 08/09/2021
-
WBALTV11: Court battle brewing over Conowingo Dam’s relicensing to Exelon - 06/17/2021
-
Chesapeake Bay Magazine: Exelon relicensed to operate Conowingo Dam for next 50 years, after long fight - 03/19/2021